Isometric circuit board and supply-chain network with one chip flagged under an inspection beam to screen for counterfeit electronic parts.

Counterfeit Electronic Parts: DFARS 252.246-7007 and 7008 Rules

Published On: November 18th, 2026|

The DFARS rules on counterfeit electronic parts rest on two clauses. DFARS 252.246-7007 requires certain contractors to establish and maintain an acceptable counterfeit electronic part detection and avoidance system. DFARS 252.246-7008, Sources of Electronic Parts, governs where the supply chain may buy, how parts are traced, and what happens when a part can only be found outside authorized channels.

This guide is for contracting staff, purchasing and supply-chain teams and program managers who need to know what the two clauses ask of primes and subcontractors. It draws on the eCFR text of DFARS subpart 246.8 and of the clause, and the Federal Register notices that explain DoD’s intent. Clause wording changes over time, so always work from the version incorporated in your own contract.

What do the DFARS clauses on counterfeit electronic parts cover?

The two clauses do different jobs, and they reach different groups of companies.

The reach of the sources rule is wide. In its 2016 final rule notice, DoD said the sourcing requirement applies to all DoD contractors and subcontractors when they obtain electronic parts to be provided to DoD under a DoD contract. It is not limited to CAS-covered companies.

A note on vocabulary. “Trusted supplier” is common shorthand, and DoD’s 2016 notice used the phrase too. The DFARS text quoted in this article works with more specific terms: original manufacturer, authorized supplier and contractor-approved supplier. Using those terms in purchase orders and supplier questionnaires makes it clearer which rule on counterfeit electronic parts applies to which source.

Who must maintain a detection and avoidance system under 252.246-7007?

The system requirement starts with CAS-covered prime contractors. DoD’s 2014 final rule clarified that the counterfeit system criteria apply only to CAS-covered prime contractors, and that the requirement flows down to all subcontractor tiers providing electronic parts or assemblies containing electronic parts.

That flow-down matters to suppliers that are not CAS-covered themselves. A distributor or reseller selling into a CAS-covered prime should expect to be asked how its own processes keep counterfeit electronic parts out of the prime’s product.

The DFARS sets out a list of criteria the system must address. Two that purchasing and quality teams deal with every day are:

Those are two items from a longer list, so read the clause for the rest. One scoping point: the DFARS prescription says not to use 252.246-7007 in solicitations and contracts that are set aside for small business. The sourcing rule is a separate matter. As noted above, DoD has said it applies to all DoD contractors and subcontractors.

What is the sourcing order of preference in 252.246-7008?

DFARS policy sorts every buy into one of three situations, and the buyer’s duties grow as you move down the list. This ordering is the practical core of the rules on counterfeit electronic parts.

  1. Parts in production or currently in stock. Parts in production by the original manufacturer or an authorized aftermarket manufacturer, or currently available in stock, must be obtained from the original manufacturers, their authorized suppliers, or suppliers that obtain the parts exclusively from those sources.
  2. Parts out of production and not in stock. Where contractor-approved suppliers are used, the contractor must identify and approve them using established counterfeit prevention industry standards and processes, including inspection, testing and authentication, such as the DoD-adopted standards at assist.dla.mil.
  3. Everything else. If a part comes from another source because of nonavailability, comes from a subcontractor that refuses to accept flowdown, cannot be confirmed as new, or cannot be confirmed as not having been commingled in supplier new production or stock with used, refurbished, reclaimed, or returned parts, the notification, inspection, testing and authentication requirements of paragraph (b)(3)(ii) of 252.246-7008 apply.

The clause defines a contractor-approved supplier as a supplier that has no contractual agreement with the original component manufacturer for a transaction, but has been identified as trustworthy by a contractor or subcontractor.

What traceability does the clause expect?

A contractor that is not the original manufacturer or an authorized supplier must have risk-based processes that enable tracking of electronic parts from the original manufacturer to product acceptance by the Government. That holds whether the part is supplied as a discrete electronic part or is contained in an assembly.

The clause also says what happens when the chain breaks. If the contractor cannot establish traceability from the original manufacturer for a specific part, it must be responsible for inspection, testing and authentication in accordance with existing applicable industry standards.

For a purchasing team, that points to a few questions to settle before the purchase order goes out:

  • Which of the three sourcing situations does this supplier fall into for this part number?
  • Can the supplier document the chain back to the original manufacturer?
  • If it cannot, who performs inspection, testing and authentication, and against which standard?
  • Does the assembly contain parts that need the same answers?

Getting those answers in writing gives you a record of how the risk of counterfeit electronic parts was handled on each buy.

How do you buy a part that authorized sources no longer carry?

Obsolescence is where the sourcing rules are tested. When a part is out of production and is not available in stock from any first-tier source, meaning the original manufacturers, their authorized suppliers, or suppliers that obtain the parts exclusively from those sources, the contractor-approved supplier tier comes into play, and the buyer takes on more of the work of guarding against counterfeit electronic parts.

Using a contractor-approved supplier. Three points from the DFARS and DoD’s 2018 final rule shape this choice:

The last point has a schedule consequence. A program that relies on a single approved source for an obsolete part may have to absorb the cost and delay itself if that source is later rejected, on top of its responsibility for keeping counterfeit electronic parts out of the build.

Going outside the preferred sources. When nonavailability forces a buy from another source, paragraph (b)(3)(ii) applies. DoD described the duty in 2016: contractors and subcontractors that are not the original component manufacturer are required to notify the contracting officer if it is not possible to obtain an electronic part from a trusted supplier. Inspection, testing and authentication go with that notification.

There is one practical easing. Where notification is required for an electronic part to be used in a designated lot of assemblies acquired under a single contract, the contractor may submit one notification for the lot.

How are suspect counterfeit electronic parts reported through GIDEP?

Reporting runs through GIDEP. Under FAR 52.246-26, where that clause is in the contract, the contractor must submit a report to GIDEP within 60 days of becoming aware or having reason to suspect that an item covered by the clause is counterfeit or suspect counterfeit, subject to exceptions in the clause, including for certain foreign contractors and ongoing criminal investigations. The clause also separately requires written notification to the contracting officer within 60 days.

The same clause tells the contractor to retain counterfeit or suspect counterfeit items in its possession at the time of discovery until the Contracting Officer provides disposition instructions. In plain terms, hold the parts and wait for instructions instead of sending them back or scrapping them.

GIDEP also works in the other direction. A 252.246-7007 system must include a process for screening GIDEP reports, so the data other companies file becomes an input to your own receiving and supplier decisions on counterfeit electronic parts.

For a sense of scale, a 2016 GAO report found that DOD agencies and contractors submitted 526 suspect counterfeit parts reports in GIDEP from fiscal years 2011 through 2015. Those figures are now more than a decade old, so treat them as background, not as a current measure.

What has to flow down to subcontractors?

Both clauses travel down the supply chain, in different ways.

Flow-down is more than a formality. If a subcontractor refuses to accept it, DFARS policy applies the same notification, inspection, testing and authentication requirements that govern buys from non-preferred sources. Agreeing the terms early avoids discovering that problem at award, and keeps the controls against counterfeit electronic parts intact at every tier.

How can purchasing teams lower the risk of counterfeit electronic parts?

The rules translate into a short working routine:

  1. Check which clauses are in the contract and whether your company, or your customer, is CAS-covered.
  2. Classify each electronic part buy: in production or in stock, out of production and not in stock, or available only from other sources.
  3. Buy from the original manufacturer or its authorized suppliers whenever the part is available there.
  4. Record traceability back to the original manufacturer, or plan inspection, testing and authentication where it cannot be established.
  5. Notify the contracting officer when paragraph (b)(3)(ii) is triggered, using a single lot notification where the clause allows it.
  6. Screen GIDEP for reports of counterfeit electronic parts, report within the FAR 52.246-26 deadline, and hold suspect items for disposition instructions.
  7. Flow the substance of the sources clause down in subcontracts for electronic parts or assemblies containing electronic parts, unless the subcontractor is the original manufacturer.

CCCS supports federal agencies and prime contractors as a value-added reseller, and compliance-first procurement is a core part of our work. Our capabilities include resale of electronic components, Tier-1 access to authorized distribution, and legacy support for hard-to-find or end-of-life components. Our services cover delivery of final Certificates of Compliance and, where a primary product is unavailable, full technical disclosure and vetting of alternative products. Buyers working under the DFARS rules on counterfeit electronic parts can ask our team how a specific requirement would be sourced and documented.

Frequently asked questions

Does DFARS 252.246-7008 apply to commercial product buys?

Yes. The DFARS prescription directs use of the clause in solicitations and contracts using FAR part 12 procedures for commercial products and commercial services, and the flow-down paragraph covers subcontracts for commercial products. A commercial label does not take a buy outside the rules on counterfeit electronic parts.

Does the Government approve contractor-approved suppliers?

Not as a matter of course. DoD said in 2018 that Government review, audit and approval of contractor-approved suppliers is not mandatory. The contractor identifies and approves them using industry standards and assumes responsibility for the authenticity of the parts. If a contracting officer disapproves a source, that is not a contract change qualifying for equitable adjustment.

How long does a contractor have to report suspect counterfeit electronic parts?

FAR 52.246-26 requires a report to GIDEP within 60 days of becoming aware or having reason to suspect that an item covered by the clause is counterfeit or suspect counterfeit, subject to exceptions in the clause, including for certain foreign contractors and ongoing criminal investigations. It also separately requires written notification to the contracting officer within 60 days. The contractor must also retain the items in its possession until the Contracting Officer provides disposition instructions.

Does 252.246-7007 apply to small businesses?

The DFARS says the system clause is not used in solicitations and contracts set aside for small business. The sourcing rule is separate: DoD has said it applies to all DoD contractors and subcontractors obtaining electronic parts for delivery to DoD. Small business suppliers therefore still need to follow the sourcing order of preference that guards against counterfeit electronic parts.

What if traceability to the original manufacturer cannot be shown?

The clause makes the contractor responsible for inspection, testing and authentication under existing applicable industry standards for that part. Where the part came from outside the preferred sources, cannot be confirmed as new, or cannot be confirmed as not having been commingled in supplier new production or stock with used, refurbished, reclaimed, or returned parts, the notification requirements of paragraph (b)(3)(ii) apply as well.

If you are sourcing electronic parts for a defense or federal program and want to talk through a hard-to-find or end-of-life requirement, make enquiry or call our experts on 1.321.951.0289.